SNB-C01: Flight Controls

  • Rudder Control System – Part 2

    Rudder Control System – Part 2

    Heated up C01-03 rudder spring stock with propane torch and bent springs to specs in plans. Previously tried to bend springs without heat and spring steel broke rather than bent. After installing springs into fuselage, discovered that plan dimensions were a little long and resulted in rudder pedals not returning to neutral. Shortened springs by…

  • Rudder Control System – Part 1

    Rudder Control System – Part 1

    Installed rudder pedals and mount blocks into fuselage. Applied white lithium grease to rudder pedals before tightening rudder pedal mount blocks. Fed rudder cables through aft fuselage and temporarily installed AN23 clevis pins into rudder horn. Installed cable fairleads into fairlead blocks. Bolted cable adjusters onto rudder pedals and marked LH cable adjuster hole per…

  • Elevator Control System – Part 1

    Elevator Control System – Part 1

    Temporarily installed control stick assembly. Pressed SF-812-3 bushings into stick to idler bar and control frame then installed idler hardware permanently and stick hardware temporarily. Verified freedom of movement and clearances with idler bar. Pressed bushing into elevator push rod ends, clecoed forward pushrod support to cross ties, and checked clearance of elevator push rod.…

  • Rudder System Installation – Part 1

    Rudder System Installation – Part 1

    Located rudder pivot blocks onto fuselage and temporarily inserted rudder pedals to check fit. Fit and function seemed good so clamped blocks to fuselage and drilled forward mounting holes. Will need to remove assembly to apply grease in future. Hours Worked: 1.17