  • Forward Fuselage Part Prep – Part 3

    Forward Fuselage Part Prep – Part 3

    Created -05 support angles from .063 sheet and legacy plans. Located them onto -04L/R rudder pedal mount angles per plans and riveted with CCC rivets to create -03L/R assemblies. Cut 2.5×2.5×0.125 angle to create -12L/R angle clips and pilot drilled to 1/8″. Edged rounded on angle clips. F15 complete! Hours Worked: 2.68

  • Forward Fuselage Part Prep – Part 2

    Forward Fuselage Part Prep – Part 2

    Created -08 clips per legacy plans out of Z01-03 stock. Up drilled -03 assembly then dimpled aft -05 tunnel angle. Countersunk -04 support channel, -12 spacer plates, and -14L/R and -15L/R angles. Refitted components together, installed MS24694 bolts for standard gear configuration, and riveted with CCC rivets. F16 complete! Hours Worked: 4.85

  • Forward Fuselage Part Prep – Part 1

    Forward Fuselage Part Prep – Part 1

    Bent trailing edge of forward fuselage floor up 5 degrees. Pilot drilled holes in top edge of -02 forward tunnel zee. Began clecoing -03 aft tunnel web assembly together. Hours Worked: 1.16

  • Firewall Prep – Part 1

    Firewall Prep – Part 1

    Creation of miscellaneous firewall components per plans. -10, -11, and -12 parts created via legacy plans set. Bent edges of -01 up per plans and set aside. -03 assembly created from firewall former halves.. Hours Worked: 2.27

  • Tail Cone Box Wrapup

    Tail Cone Box Wrapup

    Riveted turtledeck assembly to fuselage tail cone box per plans revision E. Up drilled holes through side skins and upper splice plates to 3/16″ and installed AN525 hardware. Torqued to spec. Clecoed crosstie closeout plate into place and riveted into place. Clecoed flap motor actuator mounts into place and verified alignment with flap drive tube…

  • Turtledeck Assembly – Part 8

    Turtledeck Assembly – Part 8

    Riveted formers #5 through #2 to turtledeck skin starting at upper longerons and moving towards the skin splice channel. Riveted lower #1 formers to back of cross tie box then riveted upper #1 formers to turtledeck skin assembly. Riveted F20-08 splice plate to upper skin splice channel and #1 formers. Wrapped up #1 former section…

  • Turtledeck Assembly – Part 7

    Turtledeck Assembly – Part 7

    Prepped and clecoed formers #4 through #2 to tail cone box and turtle deck skin. Prepped and clecoed #1 lower formers to cross tie box, side skins, and turtledeck skin. Prepped and clecoed upper #1 formers to turtledeck skin along with upper splice plate. Once fit and squareness was verified with tail cone assembly, final…

  • Turtledeck Assembly – Part 6

    Turtledeck Assembly – Part 6

    Deburred and prepped splice channel assembly and riveted skin splice channel and all attach angles. Deburred, scotchbrited, and acetoned LH and RH turtledeck skins and riveted to splice channel assembly to create -02 turtledeck skin assembly. Clecoed RH side of -02 assembly to aft fuselage tail cone then folded turtledeck skin over to cleco into…

  • Flap Drive Tube Installation

    Flap Drive Tube Installation

    Located flap drive angles per plans and pilot drilled/clecoed into place. Marked center of lower crosstie #1 and flap drive tube and centered flap drive tube. Marked location of flap mount blocks and drilled 3/16″ holes in lower splice plates. Needed to notch out lower crosstie #1 to clear flap mount blocks. Up drilled lower…

  • Fuselage Box Assembly – Part 10

    Fuselage Box Assembly – Part 10

    Riveted upper cross tie #2 to vertical channels and upper cross tie box to vertical channels #1. Fit cross tie splice plates to upper splice plates via AN3 bolt holes and riveted plates to cross tie box. F21 complete! Hours Worked: 0.67

  • Fuselage Box Assembly – Part 9

    Fuselage Box Assembly – Part 9

    Continued final assembly of tail cone. Started by clecoing lower cross ties and aft angle. Riveted aft angle and lower cross tie #5 in order to install aft Shear Web Assembly. Riveted shear web to aft bulkhead and lower aft angle. Un clecoed upper longerons to slip in shear Web Assembly and clecoed into place.…

  • Fuselage Box Assembly – Part 8

    Fuselage Box Assembly – Part 8

    Began reassembling aft fuselage assembly by clecoing upper and lower crossties to aft fuselage side panels. Hours Worked: 0.75