AN3-7A
-
Fuel Tank Installation
Rinsed tank out with water to clear out debris from inside. Re-fit tank to fuselage and trimmed fuel bay area slightly more to accommodate vent fitting. Clecoed tank stop into place and confirmed tank was sitting full forward. Installed fuel tank straps and lightly tightened straps until they were touching the tank fully. Used AN3-7A…
-
Forward Fuselage Part Prep – Part 2
Assembled F10-16 idler assembly (skipping -21 and -17 sub assemblies. Used vice to press in Symmco bushings to pivot angles. Lubricated bushings and pivot bearings with LPS-2 prior to assembly. Hours Worked: 0.57
-
LH Main Spar Assembly – Part 6
Bolts inserted into LH spar and torqued. LH Main spar complete! Spar test fit and final drilling of alignment holes and wing attach blocks will be separated into WC02 task Hours Worked: 3.00
-
RH Main Spar Assembly – Part 9
Completion of the riveting and bolting of the RH spar. Rivets finished, blemishes primed, and all attach angles bolted and final torqued. Did not bolt spar blocks on and clecoed left in tip web. Hours Worked: 5.75