  • Windshield Installation – Part 1

    Windshield Installation – Part 1

    August 1, 2025

    |

    SNB-D01: Canopy/Windscreen Installation

    Marked out 1″ skin overlap line on windshield skirt. Aligned skirt with windshield centering fuel door cutout in windscreen and aligned back edges together. Marked skirt location onto wind screen then pilot drilled fuel door holes in windshield with #40…

    More Details…

  • Windscreen Install Prep

    Windscreen Install Prep

    July 18, 2025

    |

    SNB-D01: Canopy/Windscreen Installation

    Removed top row of clecoes from upper longerons and upper engine mount screws to prepare for windscreen installation. Hours Worked: 2.17

    More Details…

  • Fuselage Final Riveting – Part 2

    Fuselage Final Riveting – Part 2

    July 18, 2025

    |

    SNB-F01: Fuselage Complete

    Removed forward fuselage floor for better access to forward tunnel zee. Deburred new holes in fuselage floor and new bottom holes in forward zee. Used hand riveter to flush rivet forward wing mount plates to forward tunnel zee. Hours Worked:…

    More Details…

  • Follow-up Storage Treatment #4

    Follow-up Storage Treatment #4

    July 13, 2025

    |

    Engine Maintenance

    Performed long-term storage procedure IAW Jabiru Maintenance Manual. Removed plugs and lubricated cylinders with Phillips 20W50 Anti-Rust Oil. Reinstalled plugs but did not torque. Removed rocker covers and lubricated rocker chambers with same oil. Reinstalled rocker covers but did not…

    More Details…

  • Canopy Components – Part 2

    Canopy Components – Part 2

    July 11, 2025

    |

    SNB-D03: Canopy Components

    Took SNB-D03-09L and updrilled holes per plans; inside holes to 3/16″ and outside holes to 13/64″ to be tapped. Countersunk 3/16″ holes for flush screws and tapped outside holes with 1/4″-28 tap set for canopy alignment pins. Hours Worked: 0.64

    More Details…

  • Control Stick Assembly – Part 3

    Control Stick Assembly – Part 3

    July 11, 2025

    |

    SNB-C04: Control Sticks

    Disassembled dual stick assembly and deburred stick holes. Lubricated control stick horns with lithium grease and deburred taper pin holes. Reassembled left and right control sticks and attached link rod with hardware. C04 complete! Hours Worked: 0.70

    More Details…

  • Canopy Components – Part 1

    Canopy Components – Part 1

    July 4, 2025

    |

    SNB-D03: Canopy Components

    Began canopy/windshield frame prep by working on canopy forward aft bows and windshield bow. For canopy bows, started by countersinking bow holes for -6 flush rivets. Riveted components together using -6 solid rivets. Laid out bows on workbench and marked…

    More Details…

  • Control Stick Assembly – Part 2

    Control Stick Assembly – Part 2

    July 3, 2025

    |

    SNB-C04: Control Sticks

    Set bushings into top of control stick frame with Loctite 638. Using new taper reamer, reamed LH stick grip hole and inserted taper pin. Repeated whole process for right hand stick grip and found that sticks were not parallel with…

    More Details…

  • Control Stick Assembly – Part 1

    Control Stick Assembly – Part 1

    June 29, 2025

    |

    SNB-C04: Control Sticks

    Began control stick assembly process by drilling 1/8″ pilot holes in bottom of stick grips. Removed powder coating from shaft of control stick horns by using heat, sandpaper, and scotchbrite wheel. Installed SF-2024-8 bushings into control stick frame; fit is…

    More Details…

  • Fuselage Final Riveting – Part 1

    Fuselage Final Riveting – Part 1

    June 29, 2025

    |

    SNB-F01: Fuselage Complete

    Drilled holes through spar bumpers then riveted to fuselage with spars in place. Clecoed fuselage floor into place to check fitment with all holes aligning. Transferred pilot holes from floor into bottom of forward spar tunnel assembly then updrilled to…

    More Details…

  • Wing Rigging – Part 4

    Wing Rigging – Part 4

    June 27, 2025

    |

    SNB-F02: Wing Rigging

    Removed rear spar carry through from fuselage then updrilled attach angle holes through fuselage. Removed attach angles from fuselage then deburred rear spar carry through, shear web, and attach angles. Finished riveting rear spar carry through then riveted shear web…

    More Details…

  • Wing Root Doublers – Part 2

    Wing Root Doublers – Part 2

    June 27, 2025

    |

    SNB-W01: Wing Installation

    Measured wing root doubler trim distances off of wing skin at each rivet hole and transferred measurements onto inside edge of wing root doublers. Trimmed excess material off with snips then deburred edges. Clecoed wing root doublers onto wing and…

    More Details…

←Previous Page
1 … 4 5 6 7 8 … 30
Next Page→

Categories

  • Canopy and Windshield
  • Controls
  • Electrical
  • Everything Else
  • Fuselage
  • Landing Gear
  • Powerplant
  • Tail
  • Wings

Silger Sonex

Build Log for Sonex 0849B

Get in touch with me

Warning: The information and documentation provided on this blog regarding the construction of an experimental aircraft are for reference and informational purposes only. The author assumes no liability for any injury, death, or damage resulting from the use of this information. Build and operate at your own risk.