  • Vertical Stabilizer Tips – Part 1

    Vertical Stabilizer Tips – Part 1

    April 22, 2024

    |

    SNX-T02: Horizontal Tail Assembly

    Replacement of left vert stabilizer tip and fiberglass work Hours Worked: 3.00

    More Details…

  • Rudder Rebuild – Part 7

    Rudder Rebuild – Part 7

    April 21, 2024

    |

    SNX-T08: Vertical Tail

    Finish creation of vertical tip mounting flange and final riveting of vert stabilizer assembly. Hours Worked: 4.10

    More Details…

  • Rudder Rebuild – Part 6

    Rudder Rebuild – Part 6

    April 19, 2024

    |

    SNX-T08: Vertical Tail

    Finished riveting upper hinge half and began test fitting fiberglass tip and making extra flange for removable tip. Planning on getting tip rough fitted and fasteners made and then doing final fiberglass work later down the road Hours Worked: 6.00

    More Details…

  • Rudder Rebuild – Part 5

    Rudder Rebuild – Part 5

    April 18, 2024

    |

    SNX-T08: Vertical Tail

    Removed existing rudder hinge half from vertical stabilizer, remade, and clecoed into place. Final riveting and tine adjustment still needed Hours Worked: 2.68

    More Details…

  • Rudder Rebuild – Part 4

    Rudder Rebuild – Part 4

    April 16, 2024

    |

    SNX-T08: Vertical Tail

    Completed assembly of the rudder including final drilling and riveting. Discovered Hinge Half on vertical stabilizer is misaligned and will need to be replaced and refitted Hours Worked: 6.55

    More Details…

  • Rudder Rebuild – Part 3

    Rudder Rebuild – Part 3

    April 15, 2024

    |

    SNX-T08: Vertical Tail

    Continued to work on rudder skin pre-drilling. 2 of 3 ribs pre-drilled and test fitted. Rudder horn rib remaining Hours Worked: 2.71

    More Details…

  • Rudder Rebuild – Part 2

    Rudder Rebuild – Part 2

    April 12, 2024

    |

    SNX-T13: Rudder

    Made -01 and -02 Hours Worked: 2.98

    More Details…

  • Tail Spar Reinforcement

    Tail Spar Reinforcement

    April 10, 2024

    |

    SNX-T03: Horizontal Tail

    Creation of doubler to account for edge violations in forward Spar. Decided that drilling out and replacing forward Spar would be too much work so created doubler to go on back side Hours Worked: 1.70

    More Details…

  • Rudder Rebuild – Part 1

    Rudder Rebuild – Part 1

    April 10, 2024

    |

    SNX-T13: Rudder

    Manufacture of replacement parts -04 and -06 Hours Worked: 1.18

    More Details…

  • Tail Inspection – Part 6

    Tail Inspection – Part 6

    April 9, 2024

    |

    SNX-T02: Horizontal Tail Assembly

    Inspection of previous work and removal of tip ribs for surface tip installation. Hole issues found in forward Spar and tip Rib. Will need to replace rib tip and create doubler for spar Hours Worked: 1.80

    More Details…

  • Tail Inspection – Part 5

    Tail Inspection – Part 5

    April 9, 2024

    |

    SNX-T03: Horizontal Tail

    Inspection of previous work Hours Worked: 0.28

    More Details…

  • Tail Inspection – Part 4

    Tail Inspection – Part 4

    April 9, 2024

    |

    SNX-T04: Horizontal Tail

    Inspection of previous work Hours Worked: 0.13

    More Details…

←Previous Page
1 … 21 22 23 24 25
Next Page→

Categories

  • Canopy and Windshield
  • Controls
  • Electrical
  • Everything Else
  • Fuselage
  • Landing Gear
  • Powerplant
  • Tail
  • Wings

Silger Sonex

Build Log for Sonex 0849B

Get in touch with me

Warning: The information and documentation provided on this blog regarding the construction of an experimental aircraft are for reference and informational purposes only. The author assumes no liability for any injury, death, or damage resulting from the use of this information. Build and operate at your own risk.