Vertical Stabilizer Inspection – Part 2
Inspection of vertical stabilizer skin. Holes and fit look to be good. Slight damage notated on front right lower edge of stabilizer. Hours Worked: 0.10
-
Vertical Stabilizer Inspection – Part 1
Inspect vertical stabilizer parts. Was able to see most of the parts externally but obviously not able to inspect internal components like clips. Work observed externally appears to be fine. Hours Worked: 0.40
-
Rudder Issues
Removed rudder from vertical tail assembly to inventory parts and inspect via camera. Determined that rudder is twisted and will need to replace skin. Hours Worked: 4.30
-
Initial Kit Inventory – Part 5
Finished inventory of last box of small parts Hours Worked: 2.50
-
Initial Kit Inventory – Part 4
Finished small parts/hardware inventory Hours Worked: 6.00
-
Initial Kit Inventory – Part 3
Finished inventorying most of the big parts. Only thing left is hardware in small baggies Hours Worked: 5.78
-
Initial Kit Inventory – Part 1
Pickup and transportation of kit from the EAA Chapter’s storage location Hours Worked: 2.75