  • Forward Fuselage Assembly – Part 6

    Forward Fuselage Assembly – Part 6

    January 4, 2025

    |

    SNB-F11: Fuselage Box

    Clecoed lower floor/firewall stiffener and floor stiffener into place. Deburred upper firewall and riveted to fuselage box. Deburred forward fuselage floor and clecoed into place. Will wait until very end to rivet floor into place. F11 complete! Hours Worked: 1.42

    More Details…

  • Forward Fuselage Assembly – Part 5

    Forward Fuselage Assembly – Part 5

    January 2, 2025

    |

    SNB-F11: Fuselage Box

    Deburred LH and RH fuselage side panels and countersunk wing mount angle holes then re-clecoed into place onto fuselage. Deburred, dimpled, and countersunk aft spar tunnel web and clecoed back onto side panels as separate pieces. Riveted aft spar tunnel…

    More Details…

  • Cowl Hinges – Part 1

    Cowl Hinges – Part 1

    January 1, 2025

    |

    SNB-P13: Cowling

    Creation of -08 Hinge Half from P3 piano hinge stock. Hours Worked: 0.33

    More Details…

  • Forward Fuselage Assembly – Part 4

    Forward Fuselage Assembly – Part 4

    January 1, 2025

    |

    SNB-F11: Fuselage Box

    Up drilled LH fuselage side skins and splice plates. Countersunk top longeron for flush hardware. Up drilled forward fuselage floor including bolt holes. Aligned P13-08 lower cowl hinge half then drilled and clecoed to lower firewall. Up drilled lower firewall.…

    More Details…

  • Panel Decals

    Panel Decals

    December 31, 2024

    |

    Instrument Panel Design

    Updated CAD design to include tail number and passenger warning. Modeled trim wheel and updated dimensions for GPS175. Printed out design full scale and mocked up on actual instrument panel blank Hours Worked: 4.34

    More Details…

  • Forward Fuselage Assembly – Part 3

    Forward Fuselage Assembly – Part 3

    December 30, 2024

    |

    SNB-F11: Fuselage Box

    Pilot drilled and clecoed upper/lower LH/RH splice plates to forward longerons. Removed forward wing angles and clecoed forward tunnel Z and spacer plates then refitted to forward fuselage. Determined there was no way to get aft tunnel web assembly into…

    More Details…

  • Starting to Place Components

    Starting to Place Components

    December 29, 2024

    |

    Instrument Panel Design

    Created assembly file and began fitting components to panel cutout in SolidWorks. Created rough model for switch panels and GPS175 and inserted to panels. Laid out cutouts for panel power, light dimmer, and circuit breakers. Need to model cutout for…

    More Details…

  • Forward Fuselage Assembly – Part 2

    Forward Fuselage Assembly – Part 2

    December 29, 2024

    |

    SNB-F11: Fuselage Box

    Pilot drilled bolt holes through upper and lower motor mounts, longerons, and fuselage floor. Located lower forward crosstie and pilot drilled with floor skin holes. Created jig from angle rulers to set side panel width at 40″. Fit lower firewall…

    More Details…

  • Creation of Panel CAD Model

    Creation of Panel CAD Model

    December 28, 2024

    |

    Instrument Panel Design

    Uploaded picture of panel into SolidWorks and created model of panel blank. Downloaded .STEP files of Dynon components and modeled cutouts per installation instructions. Hours Worked: 5.00

    More Details…

  • Forward Fuselage Assembly – Part 1

    Forward Fuselage Assembly – Part 1

    December 28, 2024

    |

    SNB-F11: Fuselage Box

    Clecoed left and right forward side panels to aft side skins. Removed clecoed from #1 lower cross tie and aft fuselage floor and aligned lower forward skin to existing holes. Clecoed forward and aft fuselage floors to cross tie then…

    More Details…

  • Fuselage Side Panels – Part 6

    Fuselage Side Panels – Part 6

    December 27, 2024

    |

    SNB-F12: Forward Side Panels

    Up drilled LH forward side panel then disassembled and deburred/cleaned all parts. Clecoed assembly back together and installed rivets per plans. Installed AN525 hardware as called out in plans and torqued to spec. F12-01L and F12 complete! Hours Worked: 5.00

    More Details…

  • Fuselage Side Panels – Part 5

    Fuselage Side Panels – Part 5

    December 26, 2024

    |

    SNB-F12: Forward Side Panels

    Disassembled RH forward side panel and deburred/cleaned all parts. Clecoed assembly back together and installed rivets per plans. Installed AN525 hardware as called out in plans and torqued to spec. F12-01R complete. Hours Worked: 3.97

    More Details…

←Previous Page
1 … 11 12 13 14 15 … 31
Next Page→

Categories

  • Canopy and Windshield
  • Controls
  • Electrical
  • Everything Else
  • Fuselage
  • Landing Gear
  • Powerplant
  • Tail
  • Wings

Silger Sonex

Build Log for Sonex 0849B

Get in touch with me

Warning: The information and documentation provided on this blog regarding the construction of an experimental aircraft are for reference and informational purposes only. The author assumes no liability for any injury, death, or damage resulting from the use of this information. Build and operate at your own risk.