  • LH Wing Assembly – Part 5

    LH Wing Assembly – Part 5

    August 10, 2024

    |

    SNB-W07: Wing Box

    Created W05-02 and W03-02 hinge halves from M3 piano hinge and pilot drilled/clecoed to LH wing. LH doubler clecoed onto wing and holes for root rib drilled into wing skins. Forward most row of lower forward skin holes pilot drilled…

    More Details…

  • LH Wing Assembly – Part 4

    LH Wing Assembly – Part 4

    August 9, 2024

    |

    SNB-W07: Wing Box

    Pilot drilled and clecoed bottom side of forward wing skin to LH wing. Forward-most row of holes to go Hours Worked: 1.92

    More Details…

  • LH Wing Assembly – Part 3

    LH Wing Assembly – Part 3

    August 8, 2024

    |

    SNB-W07: Wing Box

    LH forward wing skin (top side) clecoed onto main spar and upper side pilot drilled into place Hours Worked: 2.08

    More Details…

  • Trimming Wing Skins – Part 5

    Trimming Wing Skins – Part 5

    August 8, 2024

    |

    SNX-WC01: Wing Conversion

    Trimmed LH Forward wing skin to new dimensions per wing conversion plans Hours Worked: 0.55

    More Details…

  • LH Landing Light – Part 2

    LH Landing Light – Part 2

    August 8, 2024

    |

    Landing Lights

    Riveted together both sides of light mount plate. Installed #8 nutplates into mount and secured LH landing light and retaining ring to mount. Mounted complete light assembly onto forward ribs and checked operation of light Hours Worked: 0.55

    More Details…

  • LH Landing Light – Part 1

    LH Landing Light – Part 1

    August 6, 2024

    |

    Landing Lights

    Removed ribs #11 and #12 from LH wing assembly and installed #10 nutplates into rib. Also installed #6 grounding lug into #12 rib. Began trimming light mount plate and re assembled with clecoes Hours Worked: 1.57

    More Details…

  • LH Wing Assembly – Part 2

    LH Wing Assembly – Part 2

    August 6, 2024

    |

    SNB-W07: Wing Box

    Finished pilot drilling upper aft wing skin to wing rib assembly including main spar row. Flipped wing over, re-leveled, and fit/pilot drilled lower wing skin to rib assembly. Aileron bell crank supports drilled and clecoed into upper aft skin. Hours…

    More Details…

  • LH Wing Assembly – Part 1

    LH Wing Assembly – Part 1

    July 30, 2024

    |

    SNB-W07: Wing Box

    Upper aft skin aligned into place. Began pilot drilling skin starting at center of rear spar and working outwards Hours Worked: 1.85

    More Details…

  • Trimming Wing Skins – Part 4

    Trimming Wing Skins – Part 4

    July 30, 2024

    |

    SNX-WC01: Wing Conversion

    Trimmed upper and lower LH wing skins per conversion plans Hours Worked: 0.65

    More Details…

  • LH Wing Rib Assembly – Part 1

    LH Wing Rib Assembly – Part 1

    July 29, 2024

    |

    SNB-W14: Wing Ribs

    Assembled LH ribs to main spar and clecoed in place. Rear spar attached to aft ribs and up drilled to #30. Rear spar set at 19″ from wing station and locked into place with brace. Forward and aft ribs up…

    More Details…

  • Wing Storage Stand

    Wing Storage Stand

    July 23, 2024

    |

    Workshop Prep

    Creation of wing stand from builders association plans Hours Worked: 2.42

    More Details…

  • RH Wing Assembly – Part 12

    RH Wing Assembly – Part 12

    July 20, 2024

    |

    SNB-W07: Wing Box

    RH root doubler deburred and clecoed onto wing. Wing tip clecoed into place as well Hours Worked: 0.43

    More Details…

←Previous Page
1 … 12 13 14 15 16 … 23
Next Page→

Categories

  • Controls
  • Electrical
  • Everything Else
  • Fuselage
  • Landing Gear
  • Powerplant
  • Tail
  • Wings

Silger Sonex

Build Log for Sonex 0849B

Get in touch with me

Warning: The information and documentation provided on this blog regarding the construction of an experimental aircraft are for reference and informational purposes only. The author assumes no liability for any injury, death, or damage resulting from the use of this information. Build and operate at your own risk.