Lower Splice Plate Prep
Created tracing paper templates of additional 7 holes to drill in lower splice plates per detail C. Placed tracing paper on splice plates and pilot drilled holes. Located lower splice plates along lower longerons per FC01 dimensions. Removed lower cross…
-
Turtledeck Assembly – Part 1
Laid out F20-06 turtledeck skins on workbench and trimmed aft inside edges per plans. Aligned edge of RH turtledeck skin to edge of F20-07 skin splice channel and transferred holes onto top flange. Temporarily assembled -02 turtle deck skin assembly…
-
Turtledeck Prep – Part 2
Laid out and marked location of F20-10 former clips on right side of F20-07 skin splice channel per legacy plans. Temporarily attached with clecoes pending final fit with formers and fuselage. Hours Worked: 0.25
-
Fuselage Box Assembly – Part 6
Flipped fuselage tail cone onto side and began up drilling fuselage floor to #30. Left forward lower corners of floor and #1 lower cross tie at pilot size to be completed when backordered fuselage conversion parts arrive. Up drilled AN525…
-
Finally, an Engine!
Inventory of a used Jabiru 3300 six cylinder, 120 horsepower engine purchased used from a private seller in Connecticut and shipped LTL. The engine was removed from a Legend Cub so the current owner could put a larger prop on…
-
Turtledeck Prep – Part 1
Creation of -07 skin spar channel and -10, -11, and -12 clips from channel stock per legacy plans. Channel stock cut with snips and pilot holes drilled per plans Hours Worked: 2.50
-
Former Clip Creation
Creation of -07L/R former clips from F07 stock. 1/8″ radius bends made using 1/4″ drill bit in vice. Angles verified with full size plans Hours Worked: 0.95
-
Aft Fuselage Part Prep – Part 4
Used F26-05 crosstie plates to pilot drill four new holes in cross tie channel per B-Model plans. Hours Worked: 0.38
-
Splice Plate Prep
Located and pilot drilled new SNB-F26-04L/R upper splice plates to upper longerons based off of skin bend line. Located and final drilled cable fairlead blocks to #1 vertical channels. Verified alignment with rudder cable holes in vertical channels. Hours Worked:…
-
Fuselage Box Assembly – Part 5
Completed pilot drilling and clecoing of aft fuselage floor to tail cone box. Attached crosstie box to cross tie splices and #1 vertical channels and clecoed bottom sheet into place. Fuselage still sits square with cross tie in place. Hours…
-
Engine Hoist
Assembly of Harbor Freight engine hoist and small stool Hours Worked: 1.75
-
Fuselage Box Assembly – Part 4
Replaced F23-02 aft bulkhead and F23-03 forward lower mount angle with new parts and drilled 3/16″ holes for tailwheel mount. Located aft fuselage tail channel on rear of tail cone and pilot drilled and clecoed into place. Secured F23-04 aft…