  • Cowl Fiberglass Work – Part 5

    Cowl Fiberglass Work – Part 5

    July 13, 2026

    |

    SNB-P13: Cowling

    Fine sanded upper cowl with 240 grit to see if latest application of micro filled in low spots; overall looks good. Will try to use some high build primer to help with pin holes but overall upper cowl looks good.…

    More Details…

  • Oil Separator Relocation

    Oil Separator Relocation

    July 13, 2026

    |

    SNB-P01: Engine Installation

    Due to exhaust tunnel interference, removed oil separator from firewall and fabricated bracket out of scrap aluminum angle to move cannister up about 1.25″. Reinstalled oil separator and reconnected vent line. Hours Worked: 1.15

    More Details…

  • Exhaust Tunnels – Part 1

    Exhaust Tunnels – Part 1

    July 10, 2026

    |

    SNB-P01: Engine Installation

    Bent exhaust tunnels and outlet lips from firewall forward kit blanks. Made flange tool out of scrap phenolic. Bent tunnel sides using bending brake then bent mounting flanges using homemade flange tool. Aligned exhaust tunnels onto newly cut cowl openings…

    More Details…

  • Cowl Fiberglass Work – Part 4

    Cowl Fiberglass Work – Part 4

    July 10, 2026

    |

    SNB-P13: Cowling

    Removed upper cowl from lower cowl again and began sanding upper cowl. Started with 60 grit and moved up to 240 grit sandpaper to better blend transition area. Finished sanding with upper cowl mocked up onto lower cowl to better…

    More Details…

  • Cowl Fiberglass Work – Part 3

    Cowl Fiberglass Work – Part 3

    July 3, 2026

    |

    SNB-P13: Cowling

    After allowing epoxy to cure, used 60 grit sandpaper and hand sanding block to rough shape cowl curvature and knock down spatter and high spots. Tried to focus on transition areas between existing cowl and new work to make transition…

    More Details…

  • Gear Leg Fairings – Part 2

    Gear Leg Fairings – Part 2

    July 2, 2026

    |

    SNB-L06: Wheel Pants & Fairings

    Placed 1.125″ Adel clamps around LH landing gear leg and marked approximate mounting hole position on gear leg fairing. Removed fairing and drilled mounting hole in fairing. Temporarily bolted fairing to landing gear leg to mark second mount hole location…

    More Details…

  • Cowl Fiberglass Work – Part 2

    Cowl Fiberglass Work – Part 2

    July 2, 2026

    |

    SNB-P13: Cowling

    After leaving the fiberglass to cure for a couple days, marked rough cut line and gently pried the top cowling off of the bottom cowling without incident. Rough sanded upper cowl using 60 grit sand paper to level bottom edge…

    More Details…

  • Cowl Fiberglass Work – Part 1

    Cowl Fiberglass Work – Part 1

    June 29, 2026

    |

    SNB-P13: Cowling

    Prepped upper cowl for fiberglass work by cleaning areas with acetone and adding more packing tape to lower cowl. Cut (3) 32″ strips of fiberglass for each side of the cowl at 1.25, 1.50, and 1.75 inches wide. Mixed small…

    More Details…

  • Pitot Installation – Part 2

    Pitot Installation – Part 2

    June 25, 2026

    |

    SNB-W23: Pitot System

    Did some rough trimming of the RH side fuselage side panel to verify routing path of pitot/aoa tubes. Disconnected RH rudder cable to ensure all bundles were behind it then reconnected cable to rudder pedal. Drilled 1/2″ holes through fuselage…

    More Details…

  • Pitot Installation – Part 1

    Pitot Installation – Part 1

    June 24, 2026

    |

    SNB-W23: Pitot System

    Leveled fuselage then temporarily installed pitot mount into RH wing to calculate spacer size needed to level pitot tube. Made 2 0.125″ spacers (0.25″ total) out of 0.125″ aluminum sheet to place under back side of pitot tube mount. Installed…

    More Details…

  • ELT Installation

    ELT Installation

    June 19, 2026

    |

    SNB-E01: Avionics & Electrical

    Located and drilled hole for ELT antenna on aft portion of turtle deck. Secured antenna to fuselage then routed and connected coax cable from antenna to ELT. Cut hole in RH #1 former for RCPI and drilled mounting holes. Installed…

    More Details…

  • Cowl Fitment – Part 7

    Cowl Fitment – Part 7

    June 18, 2026

    |

    SNB-P13: Cowling

    Continued to sand lower edge of upper cowling in preparation of lengthening the lower edge using hand and orbital sander with 60 grit. Finished rough sanding with 120 grit discs; should now be ready for fiberglass work. Cleaned upper edge…

    More Details…

←Previous Page
1 2 3 4 5 … 38
Next Page→

Categories

  • Canopy and Windshield
  • Controls
  • Electrical
  • Everything Else
  • Finishing
  • Flight Testing
  • Fuselage
  • Landing Gear
  • Powerplant
  • Tail
  • Wings

Silger Sonex

Build Log for Sonex 0849B

Get in touch with me

Warning: The information and documentation provided on this blog regarding the construction of an experimental aircraft are for reference and informational purposes only. The author assumes no liability for any injury, death, or damage resulting from the use of this information. Build and operate at your own risk.